Capital Projects

The City of Pelham has many capital improvement projects on the books. While some are future projects or in the planning/design phase, many are also under construction. Check back often to stay up-to-date with major projects happening in Pelham. 

CAPITAL PROJECTS BY DEPARTMENT

ADMINISTRATION

Project Name Project Description Budget Amount Funding Source Status
ERP Implementation Implementation of new modules for the Enterprise ERP powered by Munis system  $1,000,000 IT Capital Reserve Underway

BALLANTRAE GOLF CLUB

Project Name Project Description Budget Amount Funding Source Status
Ballantrae Backup Water Supply This is to back up the water supply from Shelby County into Ballantrae

$4,354,688 Bond proceeds Planning/Design
18th Hole Bridge Replace worn bridge decking at the 18th hole $20,000 ARPA funds Planning/Design
Clubhouse Improvements Exterior renovations and grill modifications $1,130,897 ARPA funds/Bond proceeds/General Fund Planning/Design

DEVELOPMENT SERVICES & PUBLIC WORKS

Project Name Project Description Budget Amount Funding Source Status
City Hall City Hall renovations and upgrades $3,024,053   Bond proceeds & ARPA funds Underway
City Hall Landscaping & IT Upgrades for City Hall landscaping and Information Technology needs  $276,000  IT Capital Reserve Underway
Hydrology Study Hydrology/Drainage study for primary drainage basins and priority areas   $351,470  General Fund Underway
The Canopy City's share of the infrastructure for reimbursement of the Canopy project  $480,004   Bond proceeds Underway
Oak Mountain Trail Infrastructure Road and infrastructure improvements at the Oak Mountain Trail Development site  $620,482  General Fund Underway
Gateway Improvements Signage, landscaping, and site improvements at 31N, 52/65, and 119/65.  $182,350  General Fund Planning/Design
US 31 Lighting Replacement of Highway 31 corridor lighting with modern fixtures.  $6,171,447 Bond proceeds Planning/Design
Public Space at Library Development Site This is for public park space for new development in front of Pelham Public Library  $50,000 General Fund Planning/Design
Hwy 261 Widening City's match for the widening of Hwy 261 per the agreement with ALDOT, Hoover, and Shelby Co.  $675,000 General Fund Planning/Design
Drainage Repairs/Replacement Replacement of failing drainage culverts at Red Fox Drive/ Canterbury Road  $560,000 General Fund/Gas Tax Fund Planning/Design
Amphitheater Road Widening Widening of Amphitheater Road to add a multipurpose trail from US 31 to State Park Road  $2,896,124  Bond proceeds Planning/Design
City Hall Campus Master Plan Develop site master plan for the campus of City Hall, Water Department, Fire Department, and Police Department  $15,000 General Fund Planning/Design
CR52/US 31 Improvements City match for an ALDOT widening & intersection project $60,000 General Fund Planning/Design
Drainage Improvements This is to implement priority recommendations from the ongoing drainage study  $2,600,000 ARPA funds Future Project
Annual Street Resurfacing Annual city-wide resurfacing (Summer 2023) $750,000 General Fund Future Project
Stormwater Mapping Phase I Storm sewer network mapping to support drainage maintenance and planning $150,000 ARPA funds Future Project
Greenway Trail Extension (Phase II) This is for the trail section construction from Campus 124 Park to Amphitheater Drive.

$1,149,311 Bond proceeds Planning/Design
Greenway Trail Extension (Phases III, IV) Trail section design from City Park to Campus 124 Park.

$169,507 General Fund Future Project
NRCS Creek Clean Up Grant match for debris removal from Bishop Creek from Crosscreek Drive to US 31

$265,806 General Fund Underway
NRCS Creek Clean Up Reimbursable amount for debris removal from Bishop Creek from Crosscreek Drive to US 31

$877,159 General Fund Underway
Misc Waste Water Treatment Plant Improvements Replacement of end of life equipment at the sewer plant $1,500,000 User fees Future Project
Lift Station Remediation Annual Lift Station upgrades and maintenance $1,626,500 User fees Planning/Future Projects
SSES Rehab Phase II Ongoing remediation of the sanitary sewer collection system $2,793,633 Bond proceeds Underway
SSES Rehab Phase III
Ongoing remediation of the sanitary sewer collection system
$2,200,000 Bond proceeds Future Project
SSES - TVI Ongoing remediation of the sanitary sewer collection system $111,574 Bond proceeds Planning/Design
Grit & Grease Replacement of end of life equipment at the sewer plant $600,000 User fees Underway
Annual PVC Replacement Annual PVC water main replacement in the water system $500,000 User fees Future Project
Well Maintenance Inspections and maintenance of the pump at Heather Ridge/Chandalar/Campbell Ridge $160,000 User fees Planning/Design
Ridge Drive Water Main Replacement PVC water main replacement $866,775 User fees Planning/Design
Highway 11 Water Main Replacement PVC water main replacement $2,806,786 Bond proceeds Underway
I-65 Crossing Water Main Replacement PVC water main replacement $286,051 Bond proceeds Planning/Design
King Valley Drive Water Main Replacement PVC water main replacement $628,300 Bond proceeds Planning/Design
AMR Water Meter Replacement Water meter replacements and upgrades to a radio read system $903,947 Bond proceeds Underway

FIRE DEPARTMENT

Project Name Project Description Budget Amount Funding Source Status
Fire Station No. 2 Building renovations at Fire Station No. 2  $631,576 General Fund Underway
Fire Station No. 3 Traffic Light Emergency Fire Station Exit Light on Highway 11

$364,633 Bond proceeds Planning/Design

PARKS & RECREATION

Project Name Project Description Budget Amount Funding Source Status
Dog Park & Trail Lighting New lighting at the dog park and the south end of the City Park trail  $285,644 General Fund Planning/Design
City Park Monument Sign New marquis sign at City Park  $200,000 Parks & Rec Capital Reserve Future Project
Senior Center Pickleball Courts New pickleball courts at the Senior Center $60,000 Parks & Rec Capital Reserve Future Project
City Park Restroom Upgrades Restroom remodel at City Park

$200,000 Parks & Rec Capital Reserve Future Project
Batting Cages New batting cages at City Park $70,000 Parks & Rec Capital Reserve Future Project
Senior Center Pavilion New pavilion at the Senior Center $100,000 Parks & Rec Capital Reserve Future Project
Tennis Center Court Improvements Tennis court upgrades - lighting, fencing, resurfacing, etc $60,000 General Fund Future Project
Tennis Center Improvements Tennis Center building renovations.

$151,305 General Fund Planning/Design
Coker Park Improvements Walking track upgrades $100,000 Parks & Rec Capital Reserve Future Project
Blueberry Hill Public Space For site scooping, concepts, and cost estimates $150,000 General Fund Future Project
Splash Pad New splash pad (Location TBD) $350,000 Parks & Rec Capital Reserve Future Project
City Park Playground Playground upgrades at City Park $900,000 Parks & Rec Capital Reserve Future Project
Campus 124 Park Campus 124 Park construction $235,448 General Fund Planning/Design

PELHAM CIVIC COMPLEX & ICE ARENA

Project Name Project Description Budget Amount Funding Source Status
Roof Repairs Roof Repairs on the Civic Complex Building

$200,000 FIMP funds Future Project
Turbochiller Replacement of the ice plant for the two skating rinks $1,200,000 FIMP funds Underway
HVAC Replacement This is the HVAC replacement for the Civic Complex building $1,300,000 Capital Improvement Fund Planning/Design
Fixture & Furniture Replacement Replacement of meeting rooms and lobby furnishings for the Civic Complex $200,000 General Fund Underway
Parking Lot Construction Construction of additional parking on City acquired property $250,000 General Fund Planning/Design
Facade Improvements Exterior facade renovations and for the pedestrian plaza $830,161 Bond proceeds/General Fund Underway
         

PELHAM RACQUET CLUB

Project Name Project Description Budget Amount Funding Source Status
Clay Court Resurfacing Clay court resurfacing is required every 3 years $126,000 Parks & Rec Capital Reserve Future Project
Lobby Reconfiguration Clubhouse lower floor renovations $150,000 General Fund Future Project
Lower Entrance Improvements Additional sidewalks and walkway improvements at lower-level courts

$26,000 ARPA funds Underway

POLICE DEPARTMENT

Project Name Project Description Budget Amount Funding Source Status
Roof Replacement Replacement of end-of-life roof for the Police Department

$250,000 General Fund Future Project
Parking Lot Addition Additional parking in front of the building

$64,947 General Fund Planning/Design